Compressor Windings, CSR Terminals, and Start Devices: Practical Guide for Technicians

Single‑phase hermetic compressors use three terminals – Common (C), Start (S), and Run (R) – and a combination of overload, relay, and capacitor to start and run safely. Correctly interpreting CSR pin configuration and wiring the starting devices is critical for reliable refrigeration service work and for avoiding repeated compressor burn‑outs.


Understanding C, S, and R terminals

On most refrigeration compressors, the three pins form either a triangle or a straight line, and each pin connects to one or both motor windings inside the shell. When the original diagram is missing, technicians can still identify each terminal by measuring resistance with a digital multimeter.

Typical resistance relationships

Measurement pairIdentification ruleTypical range*
C–RRun winding (lowest resistance)About 1–5 Ω on small fractional‑HP units. 
C–SStart winding (medium resistance)Usually 3–11 Ω, often 3–5 times C–R. 
S–RStart + run (highest resistance)Equals C–S + C–R by ohm’s law. 

*Values vary by model; always compare with the manufacturer’s data sheet when available.

To confirm readings, many trainers recommend writing each resistance value on a sketch of the pin layout and checking that the highest reading equals the sum of the other two. If the numbers do not add up, the compressor may have an open winding or internal damage.​


CSR, RSIR, CSIR and PSC motor concepts

Single‑phase hermetic motors are classified by how capacitors and relays are used with start and run windings. The most common arrangements in light commercial refrigeration are RSIRPSCCSIR and CSR, each with different starting torque and component requirements.

Motor types and starting characteristics

Motor typeComponentsTypical use caseStarting torque
RSIR (Resistance Start Induction Run)Start relay + start winding, no capacitorSmall domestic refrigerators, low starting torque. Low
PSC (Permanent Split Capacitor)Run capacitor in series with start windingSmooth, efficient operation, good for low starting load. ​Low–medium
CSIR (Capacitor Start Induction Run)Start capacitor + relay, start winding only during startHigher torque for larger compressors up to ≈ 3/4 HP. High
CSR (Capacitor Start Capacitor Run)Start capacitor + run capacitor + potential or current relayVery high starting torque for hard‑start conditions. Very high

CSR systems keep a smaller run capacitor in the circuit after startup to improve power factor and running efficiency while the start capacitor is removed by the relay. These motors are common in high‑starting‑torque (HST) versions of commercial compressors where frequent cycling and high condensing pressures are expected.


Overload, PTC relay, and run capacitor wiring

The start device assembly brings together three safety‑critical components: thermal overload, relay (or PTC), and capacitor. Correct wiring ensures that line voltage reaches the run winding continuously, energizes the start winding only during startup, and disconnects the compressor when overcurrent or overheating occurs.

Typical PTC / solid‑state relay and overload wiring (120–240 V)

StepConnectionFunction
1Line (L) feeds the overload protector, which then connects to COverload opens on excessive current or shell temperature. 
2Solid‑state relay/PTC connects between C and S with start capacitor in series if CSIR/CSRProvides high initial current to start winding, then increases resistance and drops out. 
3Line (L) also connects directly to R through the control circuit (thermostat, contactor)Supplies continuous voltage to run winding during operation. 
4Run capacitor connects between S and R in PSC and CSR systemsImproves running efficiency and torque. ​

Before wiring, technicians should verify that the overload has less than 1 Ω resistance when cold and that the relay coil or PTC element shows the manufacturer’s specified resistance range. Any signs of arcing, discoloration or cracked housings are reasons to replace the start device rather than re‑use it.


Multimeter checks and safety best practices

Accurate ohm measurements and ground tests are indispensable when diagnosing compressor failures or confirming correct CSR identification. At the same time, technicians must follow lock‑out/tag‑out procedures and respect the refrigeration system’s pressure hazards.​​

Recommended testing workflow

  1. Isolate and discharge
    • Disconnect power, verify zero voltage, and discharge capacitors before touching any terminals.
  2. Ohm the windings
    • Measure all three combinations (C–R, C–S, S–R), verify the add‑up rule, and compare with catalog ohm ranges when available.
  3. Check for shorts to ground
    • Use the highest megohm setting to test between each terminal and the shell; any measurable continuity usually means the compressor is grounded and must be replaced.
  4. Verify start components
    • Measure overload resistance (<1 Ω closed) and relay / PTC resistance (3–26 Ω typical on many plug‑in designs), and confirm capacitors with a capacitance meter.
  5. Monitor running amperage
    • After re‑wiring, compare running current with the nameplate RLA or data‑sheet values; high amps may signal improper capacitor size, high head pressure or internal mechanical problems.
Compressor Windings, CSR Terminals mbsmpro

Andrea Julia configuration

Compressor windings, terminal pin configuration, and the start components used in a refrigerator or air-conditioning compressor.

1. Compressor Windings and Terminals

A single-phase compressor has three terminals:
• C (Common)
• S (Start)
• R (Run)
These three pins can be arranged in different physical positions, but their electrical function is the same.

Winding Resistance Values (Typical)

Measured using a multimeter (Ohms Ω):
• C to S (Start winding): 3 Ω – 11 Ω
• C to R (Run winding): 1 Ω – 5 Ω
• S to R = Start + Run (highest resistance)
👉 The Start winding always has higher resistance than the Run winding.

2. Electrical Connection on the Compressor

The diagram shows two possible layouts of the compressor pins.
Even if the position changes, the labels C, S, and R must be identified correctly before wiring.

3. Start Device Assembly

The start system usually consists of:
• PTC Relay (Solid State Relay)
• Overload Protector
• Run Capacitor (if used)

Functions:
• PTC Relay:
– Temporarily connects the Start winding during startup.
– Disconnects it automatically once the compressor is running.

• Overload Protector:
– Protects the compressor from overheating or overcurrent.
– Opens the circuit if temperature or current is too high.

• Run Capacitor (optional on some models):
– Improves efficiency and torque during operation.

4. Multimeter Testing (Shown in Image)

Overload Test:
• Measure front to back
• Reading should be less than 1 Ω (closed circuit)

Relay Test:
• Measure between S and R
• Normal reading: 3 Ω – 26 Ω

Abnormal readings indicate a faulty relay or overload.

5. Power Supply
• The diagram shows 120 VAC input going through:
– Overload → Relay → Compressor terminals

6. Internal Relay View

The bottom-right images show the internal structure of the relay, helping identify contacts and working condition. 

See less

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Posts

GR‑EFV45,El Araby Toshiba

The Toshiba 3‑door 16 cu.ft no‑frost silver refrigerator from El Araby is built for households that need generous storage and…

GMCC PE90HME‑4 hermetic compressor

GMCC PE90HME‑4 R134a refrigerator compressor 220‑240V 50/60Hz 265–295 W LBP RSCR motor comparison with PE65H1H‑9 and PE90H1F‑9 models